Alaoji-Onitsha transmission line: 2000 persons affected by destruction – TCN

….Company pays compensation, trains 64 youths on skills
nBy Emmanuel Iheaka
nOWERRI – The Managing Director of Transmission Company of Nigeria (TCN),
Dr Ahmed Sule Abdulaziz, has disclosed that over 2000 persons were affected in the destruction of property to make way for the reconstruction and upgrade of the Alaoji-Onitsha 330KV transmission line.
Abdulaziz stated this during the official handover of grant cheques and start-up packs to some of the affected persons in Owerri, Imo State.
nThe Managing Director, represented by the Project Manager, Engr. Omobola Adusoga Sabo, said a total of 210 persons from 32 communities were given grants after a proper evaluation of the extent they were affected.
nHe further noted that 64 youths from the 32 communities – two from each community who were trained on various skills received their start-up packs.
nThe TCN boss said the skills acquisition programme and compensation was in line with President Bola Tinubu’s commitment to the welfare of the youths.
n“We are reconstructing and upgrading the Alaoji-Onitsha 330KV circuit line. All the people on the right of way will be compensated.
n“In line with the Renewed Hope Agenda of President Bola Tinubu, all the people affected were identified – 210 persons across 32 communities and we are giving them grants to start up their businesses.
n“We are also training a total of 64 youths on various skills– two from each community and they will be given start-up packs.
n“Over 2000 persons were affected. The least each person received is N1 million based on the assessment of the effect”, the managing director stated.
nIn a remark, the Project Consultant, Basil Uzodimma, said the sponsor of the project, the African Development Bank insisted insisted that everyone affected on the right of way must be compensated.
n nRelated Stories
General NewsCELEBRATING TWO YEARS OF TRANSFORMATIONAL LEADERSHIP IN THE PRESIDENTIAL AMNESTY PROGRAMME
Tomorrow, 14TH March 2026, as we look forward to the second anniversary, we reflect on the remarkable two years since the Administrator of the Preside
General NewsPRESIDENTIAL AMNESTY PROGRAMME PHASE 3: DISREGARD PURPORTED STATEMENT ON DELAYED ITA PAYMENTS — OFFICE OF NATIONAL CHAIRMAN
The Office of the National Chairman of the Presidential Amnesty Programme Phase 3, General Elaye ThankGod Dollar Slaboh, has called on beneficiaries a